My primary Win/Win business goal for the course was to commission the waste water pretreatment system by 6/31/17. The system was commissioned on 6/20/17.  The immediate impact on the business is saving the cost of having the water hauled off site for disposal (which cost the company $100K per month in May & June).

The personal goal I chose was increasing exercise to improve health. I utilized the 1-31 tracker to help form a healthy habit of getting at least 30 minutes of physical activity three times a week. This also resulted in more family time since the activities usually involved my two sons.

- Kevin, Plant Engineer of Aurora Specialty Textiles Group